Massive construction litigation case against Miami Beach.

Featured: Case No.412

Industry: Construction

VICTORY SOCKS

All proceeds go to our favorite 'gator-friendly environmental charity (making the world a better place for our future generations) :

Waterkeepers

Waterkeeper

CASE STRATEGY

Experience is the key to the city.

CASE SUMMARY

MM&H obtained largest settlement by City of Miami Beach history ($35 million) for general contractor in dispute arising out of $500 million renovation and expansion of the historic Miami Beach Convention Center. The settlement occurred mid-trial. The claim resulted from extensive mismanagement and interference in the Project by the City and its construction management firm, Hill International, which led to staggering delays and substantial work outside the scope of the original construction agreement with the City.

CASE OUTCOME

MM&H obtained largest settlement by City of Miami Beach history.